Helen Electricity Network to carry out ground investigations between Sörnäinen and Vanhakaupunki
Helen Electricity Network will carry out ground investigations between Sörnäinen and Vanhakaupunki as part of the planning of Helsinki’s 400-kilovolt electricity network. The investigations will continue until the end of 2026. The work may cause occasional noise and temporary traffic arrangements.
The ground investigations will be carried out using drilling equipment at various locations within the planning area between Sörnäinen and Vanhakaupunki. The investigations will determine, for example, the quality of the bedrock, the depth of the bedrock surface and the thickness of the soil layers above it. The investigation data will provide planners with a more detailed understanding of the ground conditions in the area for the planning of the future underground electricity network.
The work will progress from one investigation point to another, meaning that the drilling equipment will move between different locations in the area during the investigations. Drilling will cause occasional noise in the surrounding area, and the work may result in temporary traffic arrangements.
The work will mainly be carried out during the daytime. Some of the investigation points are located close to tram lines, which may affect the timing of individual works.
“Ground investigations are a standard part of planning an underground electricity network. They help ensure that the planning is based on the most accurate possible information about the soil and bedrock conditions in the area,” says Pekka Pietarinen, Project Manager for Helsinki’s 400-kilovolt electricity network at Helen Electricity Network.
The ground investigations are scheduled to be completed by the end of 2026. The results will be used in the planning of the electricity network.
Electrification of society is increasing the need for electricity network capacity
The ground investigations are part of the planning of Helsinki’s 400-kilovolt electricity network. Growing electricity consumption and the electrification of society are increasing the need for electricity network capacity. Helen Electricity Network is therefore planning to build a new 400-kilovolt high-voltage network.
The new electricity network will strengthen Helsinki’s electricity transmission capacity and respond to growing electricity consumption. Additional capacity is needed as, among other things, heating, transport and port operations become increasingly electrified.