400 Kilovolt Network in Helsinki

We are planning a 400 kilovolt power transmission connection to Helsinki in order to meet the city’s growing electricity consumption and the requirements of the clean transition.

Background to the Construction of the 400 Kilovolt Network: Supporting the City’s Growth, Vitality, and Clean Transition

Electricity consumption in Helsinki is increasing rapidly. The principal drivers are the clean transition, which is electrifying heating and transport, and the city’s ongoing development, both of which are boosting demand.

At the same time, local electricity production is now lower than before, meaning that electricity must be transmitted from further afield. This increases the need to strengthen the grid’s capacity, ensuring that sufficient electricity is available under all circumstances.

Helsinki already has a robust and reliable electricity network, but as the city grows, major investment is required, particularly in the main grid connections. Through these investments, we will ensure that the electricity grid functions smoothly and serves our customers with minimal disruption now and in the future.

Helsinki is home to several functions and services that are vital to society, and their electricity supply must operate flawlessly at all times. Such services include healthcare, public transport, and many other critical operations. Improving security of supply is a central part of developing the electricity network. By investing in the resilience of the grid, we guarantee that both everyday services and critical functions remain operational safely and reliably, even in the event of disturbances or exceptional circumstances.

The 400 Kilovolt Voltage Level Reinforces Future Electricity Transmission

Currently, Helsinki’s main connections are based on a 110 kilovolt voltage level. To secure growing electricity use in the future, 400 kilovolt connections are also needed alongside these. Introducing the new voltage level will increase grid capacity and ensure that electricity can be transmitted smoothly to where it is most needed.

At the beginning of 2026, a change to the Electricity Market Act transferred part of the network development responsibilities to distribution system operators. As a result of the legislative amendment, local and regional 400 kilovolt networks will henceforth fall under the responsibility of the distribution system operator. In Helsinki, this means that Helen Sähköverkko Oy is responsible for developing the network from the transmission grid connection point towards the concentration of consumption.

The introduction of the new 400 kilovolt voltage level will also change the role of the existing 110 kilovolt network. In future, investments will be needed in both voltage levels to ensure that the whole system serves customers as reliably as possible.

Electricity consumption growth forecast

Year Actuals Forecast
1910 1.00 0.00
1915 5.00 0.00
1920 8.00 0.00
1925 14.00 0.00
1930 23.00 0.00
1935 25.00 0.00
1940 34.00 0.00
1945 51.00 0.00
1950 58.00 0.00
1955 105.00 0.00
1960 154.00 0.00
1965 218.00 0.00
1970 312.00 0.00
1975 375.00 0.00
1980 444.00 0.00
1985 572.00 0.00
1990 630.00 0.00
1995 647.00 0.00
2000 702.00 0.00
2005 759.00 0.00
2010 813.00 0.00
2015 766.00 0.00
2020 734.00 0.00
2025 987.00 0.00
2030 0.00 1460
2035 0.00 1620

Connection Between Sörnäinen and Vanhakaupunki

Havainnekuva Sörnäisten sähköasemasta - One Architects Oy

New electricity transmission structures are being planned for Helsinki

  • New Cable Tunnel Between Vanhakaupunki and Sörnäinen

A cable tunnel of approximately 4.2 kilometres is being planned between Vanhakaupunki and Sörnäinen. The tunnel solution was chosen because there is not enough space for 400 kilovolt transmission lines within the current street structures.

  • New 400/110 kV Substation in the Hanasaari Area

A new Sörnäinen 400/110 kilovolt substation is planned for the Hanasaari energy block area. The new substation will strengthen electricity transmission capacity and secure the area’s future energy needs.

Schedule Design partners
  • Investment decision: Q2/2026
  • Start of cable tunnel construction: Q4/2026
  • Start of construction of the Sörnäinen substation: Q4/2028
  • Commissioning of the 400 kV connection: Q4/2030
  • Project management for design: Sweco PM Oy
  • Architectural design anf principal desing: Sweco Finland Oy
  • Rock engineering design: Kalliosuunnittelu Oy Rockplan Ltd
  • Structural, geotechnical and HVAC, plumbing, electrical automation and telecommunications design: Sitowise Oy
  • Substation process design: Despro Engineering Oy

FAQ

You can change the question with arrow keys and open and close the answer with space key.
The 400‑kilovolt electricity network is the highest transmission voltage level in Finland’s power system. It is used to transfer large amounts of electricity from one grid node to another, and from these nodes onward to substations connected to the current distribution network.
Electricity consumption in Helsinki is growing rapidly, and the clean transition requires increasingly efficient electricity transmission connections. The 400‑kilovolt voltage level enables a reliable and sufficient electricity supply for a growing urban area and supports the city’s vitality.
We are initially planning to construct the first tunnel‑cable connection between Sörnäinen and Vanhakaupunki.
The current backbone connections in Helsinki operate at 110 kilovolts. However, growing electricity consumption requires greater transmission capacity, which 400‑kilovolt connections can provide. The new voltage level enhances electricity transmission efficiency and improves the reliability of the entire network.
In Helsinki, network construction is carried out with the aim of placing most of the structures underground. The project takes environmental values and urban planning principles into account in cooperation with the authorities.