Which product to choose for electricity distribution?
Companies and housing companies should investigate the electricity consumption needs of the place of use and choose the product based on this assessment.
Frequently asked questions about network service agreements
Products
Below, you will find more detailed terms and price information on the pricing of each product. For places of use with fuse size 63A or less, select general or time-based distribution. At places of use above 63A, select low-voltage distribution as the product. Medium-voltage distribution is intended for sites with their own customer transformer substation.
Companies and housing companies should investigate the electricity consumption needs of the place of use and choose the product based on this assessment.
General distribution
General distribution is particularly suitable for electricity users with low electricity consumption. The product is suitable for sites with a fuse size of 63A or less.
| VAT 0 % | VAT 25,5 % | |
|---|---|---|
| Fixed fee €/month | 4,79 | 6,01 |
| Distribution fee c/kWh | 3,54 | 4,44 |
Time-based distribution
The time-based distribution product is best suited for places of use where electricity consumption predominantly takes place at night, as the distribution price is cheaper then. The product is suitable for sites with a fuse size of 80A or less.
The daytime distribution price is valid every day from 7 a.m. to 10 p.m. The night-time distribution price is valid at other times. The power fee is determined on the basis of the third highest hourly average power metered for each month. 80% of night-time power is taken into account in invoicing. We invoice the time-based distribution product monthly.
| VAT 0 % | VAT 25,5 % | |
|---|---|---|
| Fixed fee EUR/month | 15,21 | 19,09 |
| Power fee EUR/kW/month | 1,38 | 1,73 |
| Daytime distribution c/kWh | 2,25 | 2,82 |
| Night-time distribution c/kWh | 1,18 | 1,48 |
Low-voltage distribution
Low-voltage distribution is intended for sites that require high connection power or otherwise have high electricity consumption. The product is suitable for sites with a fuse size of 80A or higher.
The winter-day distribution fee is valid in December–February from Monday to Friday from 7 a.m. to 9 p.m. At other times, the distribution fee for other times is valid. The power charge is in effect for all months of the year. The invoiced power is based on the highest hourly average power of the past month, metered between Monday and Friday between 7 a.m. and 9 p.m. Reactive power input and output are charged in accordance with the price list.
We invoice the time-based distribution product monthly.
| VAT 0 % | VAT 25,5 % | |
|---|---|---|
| Fixed fee EUR/month | 28,00 | 35,14 |
| Power fee EUR/kW/month | 4,85 | 6,09 |
| Reactive power fee €/kvar, month | 2,47 | 3,10 |
| Winter day c/kWh | 1,79 | 2,25 |
| Other times c/kWh | 0,95 | 1,19 |
Medium-voltage distribution
Medium-voltage distribution is intended for large sites connected to the electricity network at voltage levels of 10 or 20 kilovolts. Medium-voltage sites have a customer transformer substation of their own.
The winter-day distribution fee is valid in December–February from Monday to Friday from 7 a.m. to 9 p.m. At other times, the distribution fee for other times is valid. The power charge is in effect for all months of the year. The invoiced power is based on the highest hourly average power of the past month, metered between Monday and Friday between 7 a.m. and 9 p.m. Reactive power output is charged in accordance with the price list.
We invoice the medium-voltage distribution product monthly.
| VAT 0 % | VAT 25,5 % | |
|---|---|---|
| Fixed fee EUR/month | 188,83 | 236,98 |
| Power fee EUR/kW/month | 3,97 | 4,98 |
| Reactive power fee €/kvar, month | 2,47 | 3,10 |
| Winter day c/kWh | 1,52 | 1,91 |
| Other times c/kWh | 0,68 | 0,85 |
Electricity tax
| VAT 0 % | VAT 25,5 % | |
|---|---|---|
| Tax category I, c/kWh | 2,253 | 2,827515 |
| Tax category II, c/kWh | 0,063 | 0,079065 |